IT Asset Disposition & Data Center Decommissioning Scoping Document
Scoping template for FlexWorx ITAD and data center decommissioning projects including asset recovery, data destruction, and environmental compliance.
Executive Summary
This document scopes a FlexWorx IT Asset Disposition (ITAD) and/or Data Center Decommissioning engagement. FlexWorx provides certified, compliant, and environmentally responsible disposition of IT assets with full chain-of-custody tracking, NIST 800-88 data destruction, and maximum asset value recovery.
Current Asset Inventory
- Total asset count by category (servers, storage, networking, endpoints)
- Asset age, condition, and estimated residual value
- Data classification of assets (contains PII, PHI, financial data)
- Current asset tracking system and tag methodology
- Lease vs. owned equipment breakdown
- Geographic distribution of assets
- Data center facility details (power, cooling, access requirements)
- Existing ITAD vendor contracts and obligations
ITAD Requirements
- Data destruction standard (NIST 800-88, DoD 5220.22-M)
- Certificate of destruction requirements
- Asset remarketing and value recovery goals
- Environmental compliance requirements (R2, e-Stewards)
- Chain-of-custody and audit trail requirements
- Logistics and transportation specifications
- Timeline constraints and facility access windows
- Reporting and reconciliation requirements
Data Center Decommissioning Scope
- Facility details (location, size, rack count, power capacity)
- Equipment removal and deinstallation plan
- Cable management and infrastructure removal
- Environmental remediation requirements
- Coordination with facility management and landlord
- Migration dependencies (workloads moving to new location/cloud)
- Regulatory and lease obligation compliance
- Final facility condition requirements
Implementation Timeline
- Phase 1: Asset Inventory & Valuation (Weeks 1-2)
- Phase 2: Data Destruction Planning & Scheduling (Weeks 2-3)
- Phase 3: Logistics Coordination & Equipment Staging (Weeks 3-4)
- Phase 4: On-Site Decommissioning & Removal (Weeks 4-6)
- Phase 5: Data Destruction & Certification (Weeks 5-7)
- Phase 6: Remarketing, Recycling & Final Reporting (Weeks 7-10)
Deliverables
- Complete asset inventory with serial numbers and conditions
- Certificates of data destruction (per asset)
- Chain-of-custody documentation
- Asset value recovery report and revenue share
- Environmental compliance certificates (R2/e-Stewards)
- Final reconciliation report
- Facility condition sign-off documentation
Pricing Model
ITAD pricing is based on asset volume, type, and data destruction requirements. FlexWorx offers revenue-sharing on remarketed assets to offset disposition costs. Data center decommissioning is priced per-rack or per-project based on facility complexity. All services include full compliance documentation.
Ready to Start Your Project?
Submit your completed scoping document to our team for a custom proposal and implementation timeline.